Broad Bay Boating Club - Multipurpose Community Facility........ coming soon
The 2015 AGM approves the committee progress the idea of rebuilt the ageing club facilities with a new purpose built clubrooms, with a design that will incorporate some of the icon value of the existing structure.
Concept plans are created by Jeremy Whittam - Architectural Draughting Studio
Community Consultation meetings held, including gathering; needs, wishes and ideas for planning
Resource consent is granted by the Otago Regional Council (May 2016)
Aurora agreed to put new overhead wires and our old supply underground (Sept 2017)
A Feasibility Study is commissioned. Josh Bruce of Impact Consultants (published March 2018)
The funding drive is officially launched, with invited guests and opened by the mayor, with the purpose to inform and draw in wider community support. (October 2018)
Structural Engineering & Architectural Drawings completed (March 2020)
Further consultation with Te Rūnanga o Ōtākou; agreeing to support our need to move the footprint of our planned rebuild (April 2021)
Variation to Resource Consent lodged (May 2021)
Major funding secured to start rebuild project (May 2021)
Building Consent application ready to be lodged (June 2021)
The Peninsula Connection (road widening) section 4 completed (June 2021)
Variation to Resource Consent successful (July 2021)
DCC Building Consent issued (Feb 2022)